How long does it take to complete a bespoke kitchen in Warsaw?

PC Piotr Chojnowski · carpenter and owner of Meble Chojnowski · bespoke kitchens in Warsaw

“How long will it take?” is usually one of the first questions we hear from customers. That is hardly surprising, because the answer often determines the moving date, handover of the flat, or simply when the household can function normally again. The problem is that answers such as “about a month” are usually not very useful.

In Warsaw, we typically complete a bespoke kitchen within 4 to 8 weeks from design approval. This gives us enough time to prepare even more demanding projects properly, including lacquered fronts and stone worktops. In this article, I explain exactly what affects the schedule and how to plan the whole process so that you avoid unnecessary delays.

PC
Piotr Chojnowski – carpenter and owner of Meble Chojnowski

I run a joinery workshop specialising in bespoke kitchens and wardrobes in Warsaw and the surrounding area. I mainly work with Egger boards and Blum fittings. I recommend solutions suited to real everyday use and the specific space, not just what looks good in a visualisation. I carry out projects in Mokotów, Wilanów, Ursynów, Wola, Żoliborz, Ochota, Praga, Białołęka and nearby towns. If you would like to discuss your kitchen, contact us via the form.

Completed bespoke kitchen after installation – Meble Chojnowski project

1. Realistic completion time – what the figures show

One important point to understand from the outset is that installation itself is not what takes the longest. Fitting the kitchen in the flat usually takes 3 to 5 working days. Everything else happens beforehand — during the design stage, when materials are ordered, and in the workshop.

From experience

When a customer contacts us in January hoping for a new kitchen by Easter, it may seem as though there is plenty of time. With lacquered fronts and a stone worktop, however, the schedule can already become tight. The earlier we start the design, the less pressure there is just before the holidays.

2. What actually takes the most time

Design and revisions

At first, everything seems simple: a few cabinets, a worktop, appliances, and that is it. Then the details begin. A change of layout, choosing Blum systems, lighting, alterations around services, or uncertainty over the colour of the fronts — every decision adds another piece to the puzzle. Before you know it, small revisions have pushed the schedule back by another two weeks and the original plan has changed completely.

In practice, most of the delays we see are not caused by the carpenter’s work, but by repeated changes during the design stage. Every decision revisited for a second or third time adds more days. Once the design is approved, we order the materials — at that point there is no longer room for changes.

Fronts and materials

This is the most common bottleneck in the whole process. Some materials are available almost immediately, while others have a lead time:

  • laminated board fronts and Egger PerfectSense — usually available quickly
  • acrylic fronts — from a few days to two weeks, depending on the decor
  • lacquered fronts — at least 3 weeks, as the MDF has to be routed, primed, lacquered and polished
  • veneered fronts — 3 to 5 weeks, depending also on the availability of the selected veneer
  • laminate and compact HPL worktops — around one to two weeks
  • stone worktops (quartz conglomerate or sintered stone) — 3 to 5 weeks from the measurement taken after the carcasses have been installed

In practice, a single decision to change the fronts from laminate to lacquer can delay the entire project by several weeks. Not because anyone is unwilling to do the work, but because the technology simply takes time. If you have not yet chosen the material for your fronts, I recommend our separate article: an overview of materials for kitchen fronts.

Bespoke kitchen project in progress – image 2.1 Bespoke kitchen project in progress – image 2.2

Installation schedule

Good installation dates in Warsaw are often booked well in advance. The busiest periods are March to June (renovation season and handovers of new-build flats) and November to December, when customers want their kitchens ready for Christmas.

Looking for a contractor at the last minute is a considerable risk. It often leaves you choosing between an inflated price and companies with a questionable reputation. You may also come across teams taking on too many jobs at once, which almost always affects quality and creates unnecessary tension during installation.

Delays on site

A situation every contractor knows: the kitchen is ready and the dates are agreed, but then it turns out that:

  • the flooring has still not been laid, so the cabinets cannot be installed
  • the electrician has not finished, leaving no sockets above the worktop or power supply for the appliances
  • the walls have not been painted, creating a risk of damaging or staining the new fronts
  • service connections are in different positions from those shown in the design, forcing alterations to already finished cabinet carcasses

The installation then has to be postponed, which disrupts the whole schedule. That is why, when working on kitchens in Wilanów, Białołęka or Wola, we always ask about the actual progress of the renovation. We distinguish between two key dates: when the kitchen should be ready according to the plan, and when the room will technically be ready for installation.

If you are planning a full renovation, it is best to contact us while the property is still in developer condition. This allows the kitchen design to progress alongside the other works. Contact us, and we will advise you on the best time to start.

3. Step-by-step schedule

This is what a typical bespoke kitchen project in a Warsaw flat looks like:

Stage Duration What happens
Initial contact and preliminary quotation 2–5 days Exchange of information, plan, photos and initial quotation
Design 1–2 weeks Measurement, design, presentation, revisions and approval
Ordering materials 1–5 weeks Depends on the fronts, worktop and appliances — this is where lead times vary most
Production in the workshop 2–3 weeks Cutting, edging, fitting hardware and packing
Installation at your property 3–5 days Delivery, positioning, appliance connections and adjustments
Stone worktop measurement and installation 3–5 weeks after the carcasses are installed Only if a stone worktop has been selected

We never order materials before the design has received final approval. This is a strict rule that protects the customer’s budget — with lacquered fronts and stone, there is no room for even a millimetre of error. Production starts only when every detail has been confirmed.

Worth noting

The measurement for a stone worktop is taken only after the carcasses have been installed — never before. This means the kitchen is already in the flat, but for 3–5 weeks it is used without the final worktop. This is normal and there is no reliable shortcut. For customers who need to start cooking immediately, we usually recommend a laminate or compact worktop. We discuss worktop materials in more detail in our article on stone, timber and wood-effect kitchen worktops.

4. Real example: a kitchen in Wola

Project

Flat in a new development in Wola

The customer was due to take possession of the flat from the developer in March. The first contact with us was in January, before handover — we exchanged photos and plans and prepared a preliminary quotation. The customer had already made clear decisions: acrylic fronts in a light decor, a compact HPL worktop and appliances selected in advance from our offer.

After handover, we carried out the final measurement, refined the design and the customer approved it without major changes. Production took 4 weeks and installation 3 days. In total, less than 6 weeks passed from design approval to a fully functioning kitchen. The customer was cooking at home one week after moving in.

📍 Wola 🎨 Acrylic fronts 🪨 Compact HPL worktop ⏱ 6 weeks

This shows that a realistic six-week timeframe from agreement to completed kitchen can be maintained — provided the decisions have been made, standard materials are used and the renovation is properly coordinated. If the customer had chosen lacquered fronts and a stone worktop, I would add at least another 3–4 weeks.

5. Can it be done faster?

Yes, but only under specific conditions:

  • a simple design without unnecessary complications
  • standard materials available from stock (popular decors and a laminate or compact worktop)
  • no lacquered or veneered fronts and no stone worktops
  • quick, final decisions during the design stage
  • an available installation slot in our schedule

In such cases, it is sometimes possible to complete the project within 3–4 weeks. But a fast turnaround and a well-made kitchen are not always the same thing. Sometimes it is worth waiting an extra two weeks to have a kitchen that does not need remedial work.

When to be cautious about “very short lead times”

In Warsaw, we regularly meet customers after they have worked with teams that promised a kitchen “in 14 days”. It most often ends with remedial work, postponed installation dates or complaints. The bespoke kitchen design itself — after measurement, revisions and customer approval — takes at least a week, often two. Production then takes another 2–3 weeks. The numbers simply do not add up.

If someone promises a kitchen “in two weeks”, it is worth asking:

  • who will carry out the installation and whether they have references
  • whether all materials are genuinely available from stock
  • whether the price includes design, measurement, installation and connections, or whether these are charged separately
  • whether the promised date is realistic or simply intended to secure the contract

The most expensive kitchen is not an expensive one — it is a kitchen that has to be done twice.

Bespoke kitchen detail – Meble Chojnowski

6. What you can do to shorten the completion time

We are responsible for the workshop and efficient production. There are, however, several decisions on your side that can genuinely speed up the whole process and allow us to move to installation sooner:

A checklist that shortens the project more effectively than “looking for the fastest contractor”

  • all appliances selected before the design stage (technical specifications, dimensions and installation positions)
  • electrical and plumbing layouts completed in accordance with the design
  • material choices made before the design starts, not during it
  • choosing decors from ranges available from stock
  • approving the design within the agreed timeframe without returning to changes two weeks later

7. Appliances and connections – who does what

A common question when agreeing the schedule is: who connects the appliances? We follow a simple rule.

If you choose the appliances from our offer, fitting and connecting the electrical appliances is included in the price of the kitchen. We offer a wide range of brands at different price points, together with tangible benefits: appliance manufacturers offer promotional packages (the most popular promotion is the fifth appliance for PLN 1 when purchasing a set of four appliances), a 5-year warranty included at no extra cost and free installation. External companies may charge PLN 800–1,500 just to connect a full set of appliances.

If the customer buys the appliances independently, we can still fit and connect them, but this is an additional service priced separately. Appliance installation takes time and carries responsibility, and in the event of a warranty claim the manufacturer may require installation documentation that complies with its guidelines. I discuss integrated appliances in more detail elsewhere on our blog, including how to choose them, what to watch out for and how much can be saved when buying a complete set.

Summary

A realistic completion time for a bespoke kitchen in Warsaw is usually 4 to 8 weeks. The greatest problems are not caused by furniture production itself, but by design changes, material lead times, delays by other trades and starting the whole process too late.

A well-planned kitchen is almost always completed faster than one rushed through at the last minute. If you have a 2–3 month horizon, there is plenty of time. If you have only 3 weeks, we can still discuss it, but we will be clear about what is realistically possible and what is not.

Frequently asked questions

Can a bespoke kitchen be completed in 3 weeks?

It is possible, but only under a few conditions: a simple design, materials available from stock (popular decors and a laminate or compact worktop), no lacquered or veneered fronts, no stone worktops, and an available slot in our schedule. If any of these conditions is not met, a realistic timeframe is 4–6 weeks. Any promise of a “kitchen in a week” should be treated with caution.

When should you order a bespoke kitchen after taking possession of a flat?

It is best to contact us before handover, while the property is still in developer condition. This gives us time to work on the design alongside the other works. We take the final measurements only after the flooring has been laid and the walls have been finished, because this is when the dimensions are reliable. As standard, 4–6 weeks pass between the final measurement and installation, so it is worth counting backwards from your planned moving date.

How long does it take to make and install a stone worktop?

A stone worktop (quartz conglomerate or sintered stone) is made only after the carcasses have been installed — never before. Measurements are taken on the finished cabinets, and production and installation usually take 3–5 weeks from that measurement. This means the kitchen is already in place during this period but without the final worktop. Customers who need to start cooking immediately usually choose a laminate or compact HPL worktop.

What most often delays kitchen installation?

From my experience, there are three main causes. First, changes after the design has been approved, especially changing the material (for example from laminate to lacquer), which can mean starting production almost from scratch. Second, material logistics, including sudden shortages of specific decors. Finally, the room may simply not be ready: unfinished electrical work, missing flooring or freshly painted walls can all prevent installation. As a joinery workshop, we keep to our deadlines, but we need the right conditions to install the kitchen without risking damage.

Is appliance installation included in the price of the kitchen?

If you choose the appliances from our offer, yes — fitting and connecting the electrical appliances is included in the price. There are also practical benefits: promotional packages (for example, the fifth appliance for PLN 1 when purchasing a set of four), a 5-year warranty included in the price and no additional installation charge, which can cost PLN 800–1,500 with other companies. If the customer buys the appliances independently, we can still install them, but the service is priced separately.

Are the quotation and design charged for?

We prepare the initial quotation free of charge and remotely — photos and dimensioned plans are enough. If you already have your own design, we can simply prepare a cost estimate on that basis. If not, the design can be ordered from us as a separate service (around PLN 500). If you continue with us and commission the kitchen, the full design fee is credited towards the project, so in practice the design becomes free of charge.

Planning a kitchen in Warsaw?

If you are waiting to take possession of a flat or planning a renovation, get in touch with us now. Coordinating the dates is one of the keys to a smooth bespoke kitchen project. We will make sure the workshop is ready at the right time for your interior. Contact us and we will prepare a realistic schedule tailored to your project.